Case studies · Worked example

Read the evidence behind a ceiling item.

A bill gives the estimator one quantity to price. The take-off shows the rooms that contribute to it. This small, fictional example shows how to test that connection.

Inspect the detailed take-off ledger
Ceiling take-offWorked illustration
One finish across two rooms · EX-01, revision B
ScopeMeasured extentArea
Room A4.80 × 3.60 m17.28 m²
Room B3.20 × 3.60 m11.52 m²
Bill item CL-0128.80 m²

Trace the quantity back to scope.

Take the two rooms in the example. Their ceiling areas add to the bill, but that alone does not tell an estimator which finish to price or which design issue was measured.

Read the bill line

Both rooms contribute to one ceiling finish measured in square metres. First confirm the item description, its scope and the specification that defines it.

Inspect the ledger

Entries L-01 and L-02 record the dimensions and sheet revision for each room. Check the calculations against the 28.80 m² total in bill item CL-01.

Open the drawing

Find both locations on the relevant sheet and check its revision against the agreed drawing register. Record any missing detail before relying on the quantity for pricing.